Pont sur Sambre

Pont sur Sambre

Project:

Pont sur Sambre

Object:

Gas and steam power plant

Client:

Siemens AG Power Generation

End customer:

Verbund AG und POWEO

Place of implementation:

Pont sur Sambre - France

Implementation period:

May 2007 - July 2008

Contract value:

EUR 3 million

Sector:

Conventional power plant engineering

Project details


Task:

  • Cooling in summer
  • Air heating for winter operation
  • Increased noise control

Solution:

Mechanical ventilation for cooling in summer and heating in winter, with jet ventilation for the turbine hall. Ventilation systems for all neighbouring buildings, including standstill heating. Air-conditioning system, including complete design and implementation planning for the switchgear and workshop building. I&C technology with DDC, SIMATIC S7 and cabling. Use of steam generation with transfer station and room heating during winter operation and for standstill heating.